From G1: The production ramp up plan as I understand it is to average about 150 per shift in the first month which would mean under 3000 vehicles produced in the first month. They expect about 250 average per shift in the second month which is about 5000 vehicles that month. During the third month the line is expected to average 350 per shift which is about 7000 vehicles per month and the current plan is for the line to stay at this level through the reservation build period. The full production goal is 500 vehicles per shift which is over 10K per month at full volume per shift.I thought I read that after the first 9000 they were gonna shut the line for 4-5 days as they introduced the 2 lines 2 shifts, if it all goes as planned.
See "Anyone Else Think It Wont Happen?" number 882