info appreciated .... yet another question : how does the number of projected first year reservations compare to the projected number for the first year's production
Jim
That is a very good question and one I do not have an answer to.

We really have no idea and part of the problem is that we have never been given a straight answer on EM's definition of 'first year' so this could mean first calendar year of production of simply the first model year of production which could be less than a full calendar year in length.
What I can tell you is that with a single shift running at EM's projected line speed of 500 vehicles per shift it would take about 6.5 months to produce 68K vehicles. When you calculate some time to ramp up to that speed you end up with about 8-9 months to produce 68K vehicles with a single shift.