100 Preproduction Elio's To Be Built In December!!

Eliodude

Elio Enthusiast
Joined
Aug 17, 2016
Messages
26
Reaction score
25
Location
Texas
On March 11th, Elio Motors announced the intention to manufacture 100 pre-production pilot units by the end of the year at their leased faculty in Shreveport.

I was reviewing Elio's latest SEC business plan update (Form 10-12B) filled on 7/25/16.

I could not locate any reference to Elio's program to produce 100 pre-production units in calendar 2016 in this updated business plan.

Possibly Elio moved away from this goal?

Below is a link to the Elio's form 10-12B filing, makes for fascinating reading!

https://www.sec.gov/Archives/edgar/data/1531266/000121465916012757/e7211601012b.htm
 

Johnny Acree

Elio Addict
Joined
May 12, 2014
Messages
1,530
Reaction score
2,573
Looks like they are now calling them V1 units

We are in the process of refining our production plans with suppliers to start production in 15 months. The key milestones for the 15-month schedule are as follows (with E1, S1 and V1 referring to various vehicle prototype phases):



$16.0 million, net proceeds at the close of the Regulation A offering


E1 Engineering drawing release


E1 Builds begin


E1 Testing


S1 Production drawing release & tooling kickoff


Order long lead equipment


Shreveport plant integration


Initial 10 retail locations selected


Retail lease agreements signed


Service partner agreements signed


S1 Builds and production validation


Initial 10 retail stores build out complete


EPA/CARB certification complete


Start of Production V1
 

Ekh

Elio Addict
Joined
May 2, 2014
Messages
3,794
Reaction score
9,525
Location
Loveland OH
I think it has one major problem -- paying the 300 to 400 people it would take to support 100 cars in the field. Can you imagine the logistics and expense of schlepping 100 cars from place to place every few days, staying there at least two, more likely 3 or 4 days, then on to the next site? At that rate, it would take over six months just to visit the official retail center cities, let alone the many, many other locations where the Elio could be hot stuff.

Right now it takes 5 to 8 people to campaign the P5. Even if you could streamline that to 4 people to share the tasks, and had 2 cars at a time in some locations -- it's a huge job.
 

Eliodude

Elio Enthusiast
Joined
Aug 17, 2016
Messages
26
Reaction score
25
Location
Texas
Looks like they are now calling them V1 units

We are in the process of refining our production plans with suppliers to start production in 15 months. The key milestones for the 15-month schedule are as follows (with E1, S1 and V1 referring to various vehicle prototype phases):



$16.0 million, net proceeds at the close of the Regulation A offering


E1 Engineering drawing release


E1 Builds begin


E1 Testing


S1 Production drawing release & tooling kickoff


Order long lead equipment


Shreveport plant integration


Initial 10 retail locations selected


Retail lease agreements signed


Service partner agreements signed


S1 Builds and production validation


Initial 10 retail stores build out complete


EPA/CARB certification complete


Start of Production V1

It appears V1 production is the final item on the list, so I must assume that estimated consumer production is at least 15 months out under the best of circumstances.

Based upon the current SEC filing, is the proper conclusion that the completion of 100 pre-production vehicles in calendar '16 is no longer a goal?
 

Eliodude

Elio Enthusiast
Joined
Aug 17, 2016
Messages
26
Reaction score
25
Location
Texas
I was reviewing Elio's latest SEC business plan update (Form 10-12B) filled on 7/25/16.

I could not locate any reference to Elio's program to produce 100 pre-production units in calendar 2016 in this updated business plan.

Possibly Elio moved away from this goal?

Below is a link to the Elio's form 10-12B filing, makes for fascinating reading!

https://www.sec.gov/Archives/edgar/data/1531266/000121465916012757/e7211601012b.htm
 

Rickb

Elio Addict
Joined
Apr 20, 2014
Messages
7,096
Reaction score
13,966
I was reviewing Elio's latest SEC business plan update (Form 10-12B) filled on 7/25/16.

I could not locate any reference to Elio's program to produce 100 pre-production units in calendar 2016 in this updated business plan.

Possibly Elio moved away from this goal?

Below is a link to the Elio's form 10-12B filing, makes for fascinating reading!

https://www.sec.gov/Archives/edgar/data/1531266/000121465916012757/e7211601012b.htm
Fascinating reading, but not enjoyable reading.
 

Ty

Elio Addict
Joined
Feb 28, 2014
Messages
6,325
Reaction score
14,761
Location
Papillion, NE
I was reviewing Elio's latest SEC business plan update (Form 10-12B) filled on 7/25/16.

I could not locate any reference to Elio's program to produce 100 pre-production units in calendar 2016 in this updated business plan.

Possibly Elio moved away from this goal?

Below is a link to the Elio's form 10-12B filing, makes for fascinating reading!

https://www.sec.gov/Archives/edgar/data/1531266/000121465916012757/e7211601012b.htm
First paragraph on page 8 says "Incorporated into the launch is the plan that the first 100 vehicles produced will be sold to a fleet customer to provide feedback".
 

Eliodude

Elio Enthusiast
Joined
Aug 17, 2016
Messages
26
Reaction score
25
Location
Texas
First paragraph on page 8 says "Incorporated into the launch is the plan that the first 100 vehicles produced will be sold to a fleet customer to provide feedback".

Thanks for the info, but my question is concerning the original projected time frame of the 100 pre-production vehicles.

It's been 6 months since Elio announced a December '16 production date, and I was curious if the latest SEC filing confirmed this intention.

The latest SEC filing seems to offer little verification of Elio's intention to meet the projected December date.
 